Q. A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately with A beginning, the work would be completed in:
a) 10 2/3 days b) 10 1/2 days c) 10 1/4 days d) 10 1/3 days
About us:
TalentSprint Aptitude Prep channel is designed to help aspirants get ready for various competitive exams including Bank, SSC, Railways, Insurance, Campus Recruitment and other Govt exams.
The channel is well-structured into playlists at the topic level for the subjects including Quantitative Aptitude, Reasoning Ability, General Intelligence, English Language, General Awareness, Banking and Current Affairs.
In addition to the videos, there will be Live sessions by expert faculty to guide you for upcoming exams. There will also be regular posts on downloadable ebooks that can help you with offline preparation.
Happy learning!
TalentSprint Aptitude Prep
0 Comments